B
bmac
Question: I am using MS project 2000.
I have tasks A, B, C, D that are due on Tuesday 08/31.
On Wednesday 09/01 A and B are done, but C and D are not.
Tasks C and D are a type of task that cannot be done later (other, new tasks
will be scheduled ... C and D are not pushed out for completion later).
However, I do not want to delete C and D. I want to show them as "not done"
but I'd like to be able to show them in the same filters as completed tasks.
Any best practices / recommendations for dealing with this?
Thanks
bmac
I have tasks A, B, C, D that are due on Tuesday 08/31.
On Wednesday 09/01 A and B are done, but C and D are not.
Tasks C and D are a type of task that cannot be done later (other, new tasks
will be scheduled ... C and D are not pushed out for completion later).
However, I do not want to delete C and D. I want to show them as "not done"
but I'd like to be able to show them in the same filters as completed tasks.
Any best practices / recommendations for dealing with this?
Thanks
bmac