showing days insted of hours in the fields

J

Jason

hello,
I would like show "days" instead of "hours" in the actual work field. The
person that submitted a schedule to me has it setup that way. How do I do
that?

Thank you
 
J

JulieS

Hello Jason,

In the menu -- Tools > Options, Schedule tab. Select "Work is
entered in" and switch to days. This will change all work fields
including Actual Work.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
J

Jason

that worked great. thank you ;)

JulieS said:
Hello Jason,

In the menu -- Tools > Options, Schedule tab. Select "Work is
entered in" and switch to days. This will change all work fields
including Actual Work.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 