Hi

We are running EPM 2003 SP2, within the Portfolio analyser, I see all
bookings for resources against a specific project.

Is there any way within the analyzer I can see the additional information
below this i.e. the tasks within the plan they have booked to?

Cheers
Suzanne
 
J

Joel P.

There are many things you can do and customize, in terms of views, resource
outline codes, project outline codes. However you cannot drill down to the
task level in Portfolio Analyzer. That is indeed a huge limitation of
Portfolio Analyzer.

Joel Plaut
 
S

Suzanne Slade

Which is exactly what we were looking to do, so it looks like either the
Resource Assignment Reporting or the useage view within MSP.

Thanks for your help.
 
M

Manmeet Chaudhari

Hi Suzanne
Just for you information in Project Server 2007 you have Data analysis view
which is similar to Portfolio analyzer.
In data analysis you can drill down to task level.
All the custom fields you create are also available in the field list of
pivot table.
Lots of new meausures are also added by default.

Data analysis in Project Server 2007 take reporting one level ahead :)

Regards
Manmeet Chaudhari
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top