Hi guys, I'm struggling to define a project view that will allow me to showonly those tasks in a master project that have dependencies across projects. I could probably cobble something together if I could get Predecessors as a filter field, but that doesn't seem to be an option. I tried defininga custom enterprise task field to equal the value of Predecessors... that *does* show up in the filter options but has no values. The external tasksfield only shows YES when opening a subproject and viewing the ghost tasks, not the master project.
Ultimately I'm trying to get a view to show, across a program, all of the tasks in the different projects that impact each other, on one view.
Any ideas?
Ultimately I'm trying to get a view to show, across a program, all of the tasks in the different projects that impact each other, on one view.
Any ideas?