A
Anita
Hi
Using 2003 and default task type fixed duration
I have a resource called 'Buyer' assigned to 3 tasks as follows:
task1 duration 0.25 hrs 2 hrs work
task2 duration 0.25 hrs 2 hrs work
task3 duration 0.25 hrs 2 hrs work
all three things happening on same day 18th July.
It flags them in red on resource sheet and one resource graph says he is
300% allocated. Why is this? He isn't overallocated and therefore the graph
is showing incorrectly. It seems to be treating each one as 100%.
Thanks
Anita
Using 2003 and default task type fixed duration
I have a resource called 'Buyer' assigned to 3 tasks as follows:
task1 duration 0.25 hrs 2 hrs work
task2 duration 0.25 hrs 2 hrs work
task3 duration 0.25 hrs 2 hrs work
all three things happening on same day 18th July.
It flags them in red on resource sheet and one resource graph says he is
300% allocated. Why is this? He isn't overallocated and therefore the graph
is showing incorrectly. It seems to be treating each one as 100%.
Thanks
Anita