Showing progress on a summary task

E

esl1007

Morning,
Is it possible to show progress on a summary bar? If so, how? Thanking you
in advance.
 
J

Jim Aksel

Do you mean have the bar show a progress line? You can address how the
summary bars appear by selecting Format/Bar Styles... on the main menu.

Change the summary bar format to something "clear" for a fill color. Then,
add a new progress indicator and make it "show for"=Summary, "From"=Acutal
Start, "To"=Complete Through.

See if that helps
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 