J
JoeR
I have a baselined project plan. One of the tasks has a projected start date
of 8/12 finishing on 8/14. As of today, 8/17, the task has not started. Is
there a way I can show under the baseline line in the Gantt another line
showing the slippage based on the current date without resetting the start
date? So the result would be baseline start 8/14, baseline finish 8/14.
Projected start 8/17 - finish 8/19.
Thanks in advance for your assistance.
of 8/12 finishing on 8/14. As of today, 8/17, the task has not started. Is
there a way I can show under the baseline line in the Gantt another line
showing the slippage based on the current date without resetting the start
date? So the result would be baseline start 8/14, baseline finish 8/14.
Projected start 8/17 - finish 8/19.
Thanks in advance for your assistance.