Is there a way to show the progress bar (usually blue) at the summary level?
For example, I have a summary task that has three sub-tasks. I'd like to
roll-up the summary task to one line and print a Gantt with the planned and
progress (blue).

Thank you in advance for your help.

Paul Peterson
 
J

Jan De Messemaeker

Hi,

IN Bar Styles (Format,Bar Styles) add the following line:
Name... Summary Progress
Appearance: select (lower half bar, full, blue)
show for: Summary
from Start
To Complete Through

OK.


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
P

PK Consulting

This worked - thanks for your help.
Jan De Messemaeker said:
Hi,

IN Bar Styles (Format,Bar Styles) add the following line:
Name... Summary Progress
Appearance: select (lower half bar, full, blue)
show for: Summary
from Start
To Complete Through

OK.


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top