K
KellyB
Is it possible to show a split during non working times?
For example, my tasks can be completed at any time, either Day shift or
Night shift. However, if I assign a task to Night shift workers, and the
task spans 2 shifts, I want to show a split bar across the day shift, and not
a solid bar across the non-working time. I want to be able to easily show
that no work will be completed on the task during the day.
Is this possible, or does MSP always draw solid bars across non-working time?
For example, my tasks can be completed at any time, either Day shift or
Night shift. However, if I assign a task to Night shift workers, and the
task spans 2 shifts, I want to show a split bar across the day shift, and not
a solid bar across the non-working time. I want to be able to easily show
that no work will be completed on the task during the day.
Is this possible, or does MSP always draw solid bars across non-working time?