silly data on data analysis services

A

Ahmed Ghaith

Dear All,

I am administrator on project server 2007, when the resources on our stuff
make submit on his tasks the actual work appear me on analysis database is
less than the real data, could you please why this happen because this data
is a critical and may effected the cost of project.

My Example:
I make submit (8 hours) on my task.
Project manager is approve and publish for (8 hours) on my task.
When project server Build, I showing my task is ( 0.64) hours.(silly data).


Regards.
 
G

Gary L. Chefetz

Ahmed:

I think that the problem may run deeper than the OLAP cube. Do you see
similar data in task usage or resource usage views in Project? There are a
number of bugs that have been fixed covering issues like this including some
very recent fixes released in March and one coming up in April. Service Pack
2 releases next week, so you should consider updating your system to at
least SP2. If you find that issues persist, you may want to apply a more
recent post-SP2 update.

Take a look at the underlying data in Project so that we can determine
whether the bad data is coming from project or somewhere between project and
the reporting database. Specify your current system and client patch levels.

--
----------
Gary L. Chefetz, MVP
MSProjectExperts
Project Server Consulting: http://www.msprojectexperts.com
Project Server Training: http://www.projectservertraining.com
Project Server FAQS: http://www.projectserverexperts.com
Project Server Help Blog: http://www.projectserverhelp.com
 