T
TWB
Hello All,
I am trying to understand the Duration concept, and I thought I had it
down until I created a task that has 2 resources with different
calendars. First my project is using all the standard options 8am-5pm,
8 hr days, no holidays, etc.
When I do the following, everything calculates as expected:
Scenario A:
Task = Paint the walls
Duration = 5d
Assigned = Bob (8 hr day / 5 days per week)
**Work = results at 40hours over the 5 days. All is good.
Start - Finish: Thu 4/15/10 8:00AM - Wed 4/21/10 5:00PM
When I do this example, I cannot wrap my head around why it results in
6 days, as opposed to 5:
Scenario B:
Task = Paint the walls
Duration = 5d
Assigned = Bob (8 hr day / 5 days per week); Jerry (10 hr day / 4 days
per week M-Th calendar)
**Work = results at expected 80 hours, but over 6 days, Why does
duration change to 6 days?????
Start - Finish: Thu 4/15/10 8:00AM - Wed 4/21/10 7:00PM
Obviously it has something to do with the 10 hr per day individual,
but even looking at the task usage sheet, the task is spread out over
5 days not 6. Also, I thought duration was calculated based off 8
hour days (as set up in my options). If that's the case, 80 hours
work / 8 hours per day / 2 people get me to 40 hours, which is 5 days
not 6 ....
Thanks so much for any assistance!
WB in Texas
I am trying to understand the Duration concept, and I thought I had it
down until I created a task that has 2 resources with different
calendars. First my project is using all the standard options 8am-5pm,
8 hr days, no holidays, etc.
When I do the following, everything calculates as expected:
Scenario A:
Task = Paint the walls
Duration = 5d
Assigned = Bob (8 hr day / 5 days per week)
**Work = results at 40hours over the 5 days. All is good.
Start - Finish: Thu 4/15/10 8:00AM - Wed 4/21/10 5:00PM
When I do this example, I cannot wrap my head around why it results in
6 days, as opposed to 5:
Scenario B:
Task = Paint the walls
Duration = 5d
Assigned = Bob (8 hr day / 5 days per week); Jerry (10 hr day / 4 days
per week M-Th calendar)
**Work = results at expected 80 hours, but over 6 days, Why does
duration change to 6 days?????
Start - Finish: Thu 4/15/10 8:00AM - Wed 4/21/10 7:00PM
Obviously it has something to do with the 10 hr per day individual,
but even looking at the task usage sheet, the task is spread out over
5 days not 6. Also, I thought duration was calculated based off 8
hour days (as set up in my options). If that's the case, 80 hours
work / 8 hours per day / 2 people get me to 40 hours, which is 5 days
not 6 ....
Thanks so much for any assistance!
WB in Texas