M
Matt MacDonald
OK, I think this is a fairly easy question, but for the life of me I
can't figure out how to do it. Right now, cuz I'm just getting
started with Project, I'm using it more for scheduling than anything
else (ie determining when new projects and tasks can be put into
production), but also to help manage time on a day to day basis. Here
is my delema. If a resourse has 2 or more tasks assigned to it, and I
want work to occur simultaneously on each, how can I do that? For
example: Task 1 takes 3 days, task2 takes 2 days and task 3 takes 4
days. That's a total of 9 days of work. If I just put them into
project like that, it will tell me to work on task1 from start to
finish, then start task2, then task 3, finishing task 3 on the 9th
day. All that is good in theory, but in the real world, at least in
my industry, progress needs to be made on all 3 tasks simultaneously.
So in reality you might spend 2 hours of each day working on each task
until all 3 are done. How can I set that up in project to schedule
the work time automatically, without making smaller 2 or 3 hour
subtasks for each task?
Thanks,
Matt
can't figure out how to do it. Right now, cuz I'm just getting
started with Project, I'm using it more for scheduling than anything
else (ie determining when new projects and tasks can be put into
production), but also to help manage time on a day to day basis. Here
is my delema. If a resourse has 2 or more tasks assigned to it, and I
want work to occur simultaneously on each, how can I do that? For
example: Task 1 takes 3 days, task2 takes 2 days and task 3 takes 4
days. That's a total of 9 days of work. If I just put them into
project like that, it will tell me to work on task1 from start to
finish, then start task2, then task 3, finishing task 3 on the 9th
day. All that is good in theory, but in the real world, at least in
my industry, progress needs to be made on all 3 tasks simultaneously.
So in reality you might spend 2 hours of each day working on each task
until all 3 are done. How can I set that up in project to schedule
the work time automatically, without making smaller 2 or 3 hour
subtasks for each task?
Thanks,
Matt