Skills-Mv Field in Enterprise Resource View

D

Darrell

Shouldn't the Skills-Mv field be available when working in the Checked-out
Enterprise Resources view? The Skills field is there but not the Skills-Mv.
Is this a setting or a change by MS?

Darrell
 
D

Darrell

Gary,

Again being used to 2003 I wrongly assumed that the Skills-MV field could be
inserted into the resource sheet used for editing the enterprise respurce
pool in Project Pro. It seems the Skills-MV is only available in the PWA edit
resource information view. So I had to select the resources and edit them one
by one "save and continue" in the PWA view versus using the resource sheet in
Project Pro. Waiting for each page to load takes longer than selecting from a
drop down in Projet Pro but it works just the same.

Darrell
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top