I have a Master project which contains a number of subprojects.
A task in the Master project (Let's call it Task 1) is dependant on 2 of the
subprojects and one of these subjects finishes 1 month later than the other.
In this case why doesn't the other subproject show 1 month's total slack ?
A task in the Master project (Let's call it Task 1) is dependant on 2 of the
subprojects and one of these subjects finishes 1 month later than the other.
In this case why doesn't the other subproject show 1 month's total slack ?