There are tasks in my project that are subject to De commitment by my
resources. I understand the difference between free and total slack. If I
have enough time in total slack but not enough time in free slack, how do I
track all of the effected tasks, in the project, if I decide to delay the
task (within the boundaries of total slack)? I have tried to create
mathematical equations (with a new column) with regard to predecessores and
successors, but have been unsuccessful.