C
Curious
Some basics: Project 2003 on XP. All tasks are Fixed Unit ASAP. All
dependencies are either FS or FF. All Resources have start dates but
NA for end dates. Scheduling based on Start Date. No assignments to
summary Tasks.
How can I specify a minimum assignment interval for a project? Say 1
hour?
Can I assign 2 people to one task without requiring them to work
together every minute? I'd like to set a time window (say, a 5 day
period) during which they're scheduled for 1 day each, but the
specific times do not have to match.
What causes Project to allocate 100s of thousands of percent to a
Resource when leveling?
What causes Project to decide to schedule some tasks in 2049 when
leveling? (Note basics above.) I've read about reasons that Project
has for doing this, but I don't think they apply in my case.
What causes Project to set Work to 0 for some rgoups of tasks when
leveling?
Is there any way to give Project a threshhold when leveling so that it
would consider an x% overallocation close enough and keep going?
Why does Project leveling assign 7.98 hours to the first day of a 3
day task, when the task has only 1 resource assigned, and the resource
has no other assignments on that day?
When I apply the "Critical" filter in Gantt, Project shows only tasks
in the final three months of the project. Does this mean that no
individual task is critical before that time? (That there are multiple
paths that prevent an earlier finish date?)
When you assign two resources to one task, both at 100%, why does Work
sometimes show slightly (8.03 vs 7.97) different values on Tracking
Gantt and Resource Usage?
What does an assignment of 0h mean and why does leveling create them?
What does it mean to assign a resource to a summary task while leaving
the detail tasks unassigned?
When you enter a work # on a task with multiple resources, why does it
divide the work # by the # of resources? And why does it not do so if
you reenter the #?
Why are the IDs sometimes out of sequence in Tracking Gantt view?
I'm happy to break this message up into individual ones if that's the
practice of the board...
dependencies are either FS or FF. All Resources have start dates but
NA for end dates. Scheduling based on Start Date. No assignments to
summary Tasks.
How can I specify a minimum assignment interval for a project? Say 1
hour?
Can I assign 2 people to one task without requiring them to work
together every minute? I'd like to set a time window (say, a 5 day
period) during which they're scheduled for 1 day each, but the
specific times do not have to match.
What causes Project to allocate 100s of thousands of percent to a
Resource when leveling?
What causes Project to decide to schedule some tasks in 2049 when
leveling? (Note basics above.) I've read about reasons that Project
has for doing this, but I don't think they apply in my case.
What causes Project to set Work to 0 for some rgoups of tasks when
leveling?
Is there any way to give Project a threshhold when leveling so that it
would consider an x% overallocation close enough and keep going?
Why does Project leveling assign 7.98 hours to the first day of a 3
day task, when the task has only 1 resource assigned, and the resource
has no other assignments on that day?
When I apply the "Critical" filter in Gantt, Project shows only tasks
in the final three months of the project. Does this mean that no
individual task is critical before that time? (That there are multiple
paths that prevent an earlier finish date?)
When you assign two resources to one task, both at 100%, why does Work
sometimes show slightly (8.03 vs 7.97) different values on Tracking
Gantt and Resource Usage?
What does an assignment of 0h mean and why does leveling create them?
What does it mean to assign a resource to a summary task while leaving
the detail tasks unassigned?
When you enter a work # on a task with multiple resources, why does it
divide the work # by the # of resources? And why does it not do so if
you reenter the #?
Why are the IDs sometimes out of sequence in Tracking Gantt view?
I'm happy to break this message up into individual ones if that's the
practice of the board...