Some Actual Hours not posting to Schedule

C

Cherylp

We are running Microsoft project server 2007. On numerous tasks (but not
all!) on my and other's published schedule, Actual Work is not being updated
after a resource submits updates through My Tasks. For example, for week 52
a resource submitted time to 7 tasks - 3 of them updated 4 did not. They did
the My Task update correctly (I watched them) and the time IS showing in the
Data Analysis view.
 
M

Marc Soester [MVP]

Cheryl,

when you say that the data analyser displays the data correctly, are you
refering to the actual work accepted from the PM into the Schedule, or do you
talk about the timesheet which was updated by the user?
Also do you use timeseheet and task update?
Thanks
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top