S
Steve Lundwall
I've been reading and reading in these forums and have picked up a great
deal of information. Thank you all for your wonderful advice and input. Now
I have to get a little more specific about our particular situation as we
proceed forward. You may want to answer this here or you may want to direct
me to a book or two (and I may already have). I realize I'll be asking for a
large body of knowledge to be consolidated into an email reply and if it was
that easy then everyone could do this. So, I guess I'm asking for very high
level advice.
We are running Project Server 2003 on Windows Server 2003 and Sharepoint
Services connected to SQL Server on a different machine. All is set up and
running fine. Our division is comprised of myself (Project Manager), 3
business analysts, 6 developers (FoxPro, .NET, Crystal and Dreamweaver), an
Oracle/SQL DBA, a security administrator and a couple of LAN Techs. We are
supporting 'Twilight' technology (old FoxPro 2.6 and 6.0 applications) and
are starting to replace them with new technology (.NET - Oracle)
applications. In addition we will be bringing in a consulting team to start
an Oracle Financials development process on 7/1/2005. We have divided up
into two teams. Unfortunately we can't stop all new development in FoxPro
and simply maintain these applications until such time as we can switch over
to new technology so there are considerable development projects on both
teams. We try to keep resources focused on their own areas but there are
some projects that we are required to do out of logical order because of
some directive from some 800 lbs gorilla. These can 'mix' technologies -
using views in Oracle of FoxPro data for example.
As project manager my experiences have always been with stand alone versions
of Project. This is our first effort into a collaborative tool and from what
I see Project and Sharepoint can be really helpful but will also require
proper planning and set up on my part to make this work correctly. It is my
intent on the new development effort to set up a master project but only
publish the sub-projects so that resources can put time and other items
against these. The older technology projects are much more fluid. We have a
few larger twilight technology development efforts which I can and will set
up as projects with proper resources and time frames but then fires happen
which can take considerable resources for a day to a week to address as
these are still mission critical applications.
So I have several questions. This may be too much for this forum so I'll be
happy to go where ever you tell me for help, advice and input. (Believe me,
people tell me where to go every day!) What I don't have the luxury of is
time and money to go to courses and attend formalized training. This is
going to have to long nights, reading, web casts, experimenting and effort
on my part.
1.. I know these forums are great sources of information. What other
places on the web offer good 'best practices' advice - especially to Project
Server newcomers?
2.. Is my new technology understanding of master projects and sub-projects
correct?
3.. How should I best set up these older technology efforts?
1.. Is it reasonable to use Project, Project Server and possibly the
Issues capability as a form of HelpDesk?
2.. Should I set up what I know about the larger projects and then 'drop
in' these emergencies (essentially 'help desk' tickets) that require
immediately analyst and developer time as sub-projects so I can show the
resulting effect on resources?
3.. Is it even reasonable to attempt to incorporate these help desk
items in Project with Sharepoint? (I like the idea of including these
significant ones in order to show effect on time and so we can use the
document sharing capabilities of Sharepoint for these efforts.)
I know this may be way too much in this forum and I'm sorry if it is. But
even just writing this out helped me understand some of the significant
learning curve I have in front of me. I'm excited by the challenge in front
of me but I know if this is set up write then management will have the views
into status, resources and utilization that they've always wanted. Thanks
again.
Steve
deal of information. Thank you all for your wonderful advice and input. Now
I have to get a little more specific about our particular situation as we
proceed forward. You may want to answer this here or you may want to direct
me to a book or two (and I may already have). I realize I'll be asking for a
large body of knowledge to be consolidated into an email reply and if it was
that easy then everyone could do this. So, I guess I'm asking for very high
level advice.
We are running Project Server 2003 on Windows Server 2003 and Sharepoint
Services connected to SQL Server on a different machine. All is set up and
running fine. Our division is comprised of myself (Project Manager), 3
business analysts, 6 developers (FoxPro, .NET, Crystal and Dreamweaver), an
Oracle/SQL DBA, a security administrator and a couple of LAN Techs. We are
supporting 'Twilight' technology (old FoxPro 2.6 and 6.0 applications) and
are starting to replace them with new technology (.NET - Oracle)
applications. In addition we will be bringing in a consulting team to start
an Oracle Financials development process on 7/1/2005. We have divided up
into two teams. Unfortunately we can't stop all new development in FoxPro
and simply maintain these applications until such time as we can switch over
to new technology so there are considerable development projects on both
teams. We try to keep resources focused on their own areas but there are
some projects that we are required to do out of logical order because of
some directive from some 800 lbs gorilla. These can 'mix' technologies -
using views in Oracle of FoxPro data for example.
As project manager my experiences have always been with stand alone versions
of Project. This is our first effort into a collaborative tool and from what
I see Project and Sharepoint can be really helpful but will also require
proper planning and set up on my part to make this work correctly. It is my
intent on the new development effort to set up a master project but only
publish the sub-projects so that resources can put time and other items
against these. The older technology projects are much more fluid. We have a
few larger twilight technology development efforts which I can and will set
up as projects with proper resources and time frames but then fires happen
which can take considerable resources for a day to a week to address as
these are still mission critical applications.
So I have several questions. This may be too much for this forum so I'll be
happy to go where ever you tell me for help, advice and input. (Believe me,
people tell me where to go every day!) What I don't have the luxury of is
time and money to go to courses and attend formalized training. This is
going to have to long nights, reading, web casts, experimenting and effort
on my part.
1.. I know these forums are great sources of information. What other
places on the web offer good 'best practices' advice - especially to Project
Server newcomers?
2.. Is my new technology understanding of master projects and sub-projects
correct?
3.. How should I best set up these older technology efforts?
1.. Is it reasonable to use Project, Project Server and possibly the
Issues capability as a form of HelpDesk?
2.. Should I set up what I know about the larger projects and then 'drop
in' these emergencies (essentially 'help desk' tickets) that require
immediately analyst and developer time as sub-projects so I can show the
resulting effect on resources?
3.. Is it even reasonable to attempt to incorporate these help desk
items in Project with Sharepoint? (I like the idea of including these
significant ones in order to show effect on time and so we can use the
document sharing capabilities of Sharepoint for these efforts.)
I know this may be way too much in this forum and I'm sorry if it is. But
even just writing this out helped me understand some of the significant
learning curve I have in front of me. I'm excited by the challenge in front
of me but I know if this is set up write then management will have the views
into status, resources and utilization that they've always wanted. Thanks
again.
Steve