Dee
Hi,
We have this issue where sometimes the OLAP cube seems to not refresh
all data. It does say that the refresh was complete but some resources'
actual hours for the day before do not appear in the analyzer views.
We have verified that the resource did send the updates and project
manager did accept the updates before the OLAP build. So we cannot
point at the resource or the PM.
The only odd thing that I've noticed sometimes (not in all cases) is
that the project was not checked in that day before the OLAP build
happened.
Is it a best practice to check in/close all project files every day?
Does anyone know if leaving the projects checked out hinders the OLAP
refresh for that project's data?
TIA
Best Regards,
Dee
We have this issue where sometimes the OLAP cube seems to not refresh
all data. It does say that the refresh was complete but some resources'
actual hours for the day before do not appear in the analyzer views.
We have verified that the resource did send the updates and project
manager did accept the updates before the OLAP build. So we cannot
point at the resource or the PM.
The only odd thing that I've noticed sometimes (not in all cases) is
that the project was not checked in that day before the OLAP build
happened.
Is it a best practice to check in/close all project files every day?
Does anyone know if leaving the projects checked out hinders the OLAP
refresh for that project's data?
TIA