B
BigFish311
I was going thru my project and noticed that some of the summary bars are
carrying different dates then the activities within it. I was unsure of
where they might be pulling the info from.
For ex.
Start Finish
Summary 1 10/25/04 5/25/05
Activity 1 12/16/04 4/20/05
Activity 2 1/20/05 5/25/05
Now if they were the only 2 activities below this summary, where would that
summary bar be pulling that 10/25/04 start date from if the other's start
dates where out further.
Thanks.
carrying different dates then the activities within it. I was unsure of
where they might be pulling the info from.
For ex.
Start Finish
Summary 1 10/25/04 5/25/05
Activity 1 12/16/04 4/20/05
Activity 2 1/20/05 5/25/05
Now if they were the only 2 activities below this summary, where would that
summary bar be pulling that 10/25/04 start date from if the other's start
dates where out further.
Thanks.