Some of the Summary bars in the file contain different dates!!

B

BigFish311

I was going thru my project and noticed that some of the summary bars are
carrying different dates then the activities within it. I was unsure of
where they might be pulling the info from.
For ex.
Start Finish
Summary 1 10/25/04 5/25/05
Activity 1 12/16/04 4/20/05
Activity 2 1/20/05 5/25/05

Now if they were the only 2 activities below this summary, where would that
summary bar be pulling that 10/25/04 start date from if the other's start
dates where out further.

Thanks.
 
J

JulieD

Hi

i last saw this behaviour in a project file that was basically corrupt.
What had happened was that there were lots of changes to the file and tasks
links had been created between a summary task and a sub-task further down
the project file (at this point in time the sub-task was part of another
summary), the sub-task then got moved to be a sub-task of the summary task
it was linked to (which project doesn't like) and a circular reference was
created which also caused the dates to go like the ones you showed below.

the file was "fixed" by the method outlined at
http://www.mvps.org/project/faqs.htm

FAQ number 43

-

Hope this helps
Cheers
JulieD
 
J

JulieD

Hi John

of course (something i never do!) ... and hopefully the problem for the OP

Cheers
julieD
 
J

John

JulieD said:
Hi

i last saw this behaviour in a project file that was basically corrupt.
What had happened was that there were lots of changes to the file and tasks
links had been created between a summary task and a sub-task further down
the project file (at this point in time the sub-task was part of another
summary), the sub-task then got moved to be a sub-task of the summary task
it was linked to (which project doesn't like) and a circular reference was
created which also caused the dates to go like the ones you showed below.

the file was "fixed" by the method outlined at
http://www.mvps.org/project/faqs.htm

FAQ number 43

-

Hope this helps
Cheers
JulieD

Julie,
The noted behavior will also occur is Options/Calculation is set to
Manual.

John
 
B

BigFish311

I did have calculation set on manual but the dates on the summary activity
stayed in place even after the file had been calculated.
 
J

JackD

You might check to see that the file is sorted correctly. Do this from
project menu and sort by ID.
 