Hi

I've added all the tasks and resources in my plan and started to look at levelling resource. To my surprise only some of the days where resources are overallocated are showing in red. I've checked the task and resource information and can't see what could be causing it.

I've attached a screen shot of a summary line for 1 particular resource but this is happening on different resources (so not related to default hours or availability). On a couple of the days even the tasks and duration are identical but some are displaying red and others not.

Does anyone have any suggestions on what the reason could be?

:confused:
 

Attachments

  • Project screen shot.png
    Project screen shot.png
    17.3 KB · Views: 388

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top