W
Waz
I posted this question earlier on the "General" forum and didn't get a
response, so I am trying here (although I know next to nothing about VBA so
please have pity on me).
I have several small sub-projects in one file (Project 2003). Each subproject
is represented by a summary bar with tasks underneath, and each contains the
same 8 activities. The activities are linked FS within each subproject and
there
are no links between subprojects. I have created bar styles to roll up the
individual activities to their respective summary bars.
What I would like to do now is sort the summary bars not by their earliest
start date, but by the start date of the sixth “child†activity in the string
of activities
underneath them.
I think the solution might entail using VBA to somehow copy the start date
of the desired task up to the summary level. On Jack Dahlgren’s page I saw a
macro to copy data from the summary level activity to the lower level tasks.
Can the opposite be done – copy from the lower level to the summary level?
response, so I am trying here (although I know next to nothing about VBA so
please have pity on me).
I have several small sub-projects in one file (Project 2003). Each subproject
is represented by a summary bar with tasks underneath, and each contains the
same 8 activities. The activities are linked FS within each subproject and
there
are no links between subprojects. I have created bar styles to roll up the
individual activities to their respective summary bars.
What I would like to do now is sort the summary bars not by their earliest
start date, but by the start date of the sixth “child†activity in the string
of activities
underneath them.
I think the solution might entail using VBA to somehow copy the start date
of the desired task up to the summary level. On Jack Dahlgren’s page I saw a
macro to copy data from the summary level activity to the lower level tasks.
Can the opposite be done – copy from the lower level to the summary level?