Waz
I have several small sub-projects in one file (Project 2003). Each subproject
is represented by a summary bar with tasks underneath, and contains the same
8 activities. The activities are linked FS within each subproject and there
are no links between subprojects. I have created bar styles to roll up the
individual activities to their respective summary bars. What I would like to
do now is sort the summary bars not by their earliest start date, but by the
start date of the sixth “child†activity in the string of activities
underneath them.
I think the solution might entail using VBA to somehow copy the start date
of the desired task up to the summary level. On Jack Dahlgren’s page I saw a
macro to copy data from the summary level activity to the lower level tasks.
Can the opposite be done – copy from the lower level to the summary level?
is represented by a summary bar with tasks underneath, and contains the same
8 activities. The activities are linked FS within each subproject and there
are no links between subprojects. I have created bar styles to roll up the
individual activities to their respective summary bars. What I would like to
do now is sort the summary bars not by their earliest start date, but by the
start date of the sixth “child†activity in the string of activities
underneath them.
I think the solution might entail using VBA to somehow copy the start date
of the desired task up to the summary level. On Jack Dahlgren’s page I saw a
macro to copy data from the summary level activity to the lower level tasks.
Can the opposite be done – copy from the lower level to the summary level?