cscap
I have several sub-projects linked into a master. Each has a manual WBS
Structure which is related to Tasks in the Master. After sorting on manual
WBS Structure in the Master, I want to be able to automatically roll up to a
summary task in the Master with sub-tasks from the sub-projects. The Problem
seems to be after I sort, and I get all the Sub-Project tasks under the
appropriate Master Tasks,I can't seem to produce a rollup number.
example after sort
Wbs Task Work
1.1 MasterOneTask 0 hrs
1.1.1 SubProj1Task 1 Hr
1.1.2 SubProj2Task 2 Hr
I want MasterOneTask to be 3 hrs.
Structure which is related to Tasks in the Master. After sorting on manual
WBS Structure in the Master, I want to be able to automatically roll up to a
summary task in the Master with sub-tasks from the sub-projects. The Problem
seems to be after I sort, and I get all the Sub-Project tasks under the
appropriate Master Tasks,I can't seem to produce a rollup number.
example after sort
Wbs Task Work
1.1 MasterOneTask 0 hrs
1.1.1 SubProj1Task 1 Hr
1.1.2 SubProj2Task 2 Hr
I want MasterOneTask to be 3 hrs.