Hi,
I want to sort all the tasks in the project by end date (not only within
grouping), by end date. In the past, I exported to Excel and then
re-created the 'hierarchy' (indent) by adding additional columns to represent
the sections, and then sorting the entire sheet by date. This allows me to
see both the task and the section it came from, I find it quite useful in
managing the team ;-). But it takes time and recreating the indents is
quite tedious. Anyone have a better way? I was told I could 'simply' sort
the tasks in Project itself, but so far, haven't been able to figure it out.
Thanks in advance!
Geri
I want to sort all the tasks in the project by end date (not only within
grouping), by end date. In the past, I exported to Excel and then
re-created the 'hierarchy' (indent) by adding additional columns to represent
the sections, and then sorting the entire sheet by date. This allows me to
see both the task and the section it came from, I find it quite useful in
managing the team ;-). But it takes time and recreating the indents is
quite tedious. Anyone have a better way? I was told I could 'simply' sort
the tasks in Project itself, but so far, haven't been able to figure it out.
Thanks in advance!
Geri