SP2 & June CU Updates - Client Server Dependencies?

C

chicagohunter

Hello All - we have a global deployment of Project Pro & Project Server 2007.
Does anyone know if there are any dependencies, gotchas, etc. regarding the
client and server patch level? Updating our servers is faster and easier than
updating our clients so we usually start deploying the client updates several
weeks before our production server upgrade. Are there any issues with having
the Project Pro client running SP2 w/June CU with the servers still on an
older patch level?

Any info you can provide will be appreciated - thank you.
 
G

Gary Chefetz

My one word of advice here is not to deploy SP2 to any Project Server
Administrators until the enterprise global bug is fixed in the August CU.
 