Hey guys,

Just wondering; is there any way to assign specific calender dates to
project? Such as flights, or specific days off with explanations listed
Such as a note on a calender day; or a paid day off? By which I refer t
a day where other tasks must overlap / ignore, but to which the sai
resource is still being expended?

Regards,
Na
 
M

Mike Glen

Hi Naijan ,

Welcome to this Microsoft Project newsgroup :)

In Project 2007, Tools/Options.../Change Working Time, select the date and
enter a pertinent description in the Exceptions dialog below.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top