Special Project Hours

B

bkoren

In general, I have my resources set up to work 8 hour weekdays. I have a
special project where my resources will work 11 hour days and include
Saturdays. Is there a way to reflect this in MS Project 2007?

I appreciate any input.

Thanks,
Barb
 
J

JulieS

Hello Barb,

Yes, you can modify the calendar in Project 2007 to reflect the 11
hour days and set Saturdays as working times. See FAQ 5 at
http://project.mvps.org/faqs.htm to get you going. Make sure you
change not only the project calendar but the definition of Days and
Weeks as well on Tools > Options, Calendar tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 