B
bkoren
In general, I have my resources set up to work 8 hour weekdays. I have a
special project where my resources will work 11 hour days and include
Saturdays. Is there a way to reflect this in MS Project 2007?
I appreciate any input.
Thanks,
Barb
special project where my resources will work 11 hour days and include
Saturdays. Is there a way to reflect this in MS Project 2007?
I appreciate any input.
Thanks,
Barb