X
Xavier
Hello,
I have to create a Consulting task in the project. How can I create this.
3day effort which will be done from 1.7.2007 till 28.7.2007.
In this month there are a lot of tasks, but the consultancy is on the
complete month with an effort of 1 hour per day
Thanks
I have to create a Consulting task in the project. How can I create this.
3day effort which will be done from 1.7.2007 till 28.7.2007.
In this month there are a lot of tasks, but the consultancy is on the
complete month with an effort of 1 hour per day
Thanks