Hello,
we are currently implement project server into our company. We have a
'admin' project setup with a task called "Vacation". If a resource wants a
certain day off they go to there time sheet and book out 7hrs on that task.
Once approved they can take the day off. The question I have is there a way
to to update the specific resources calendar (book out non working time
within the resource pool) so that other project schedules can pick up on
this?