J
Joe
Is it possible to assign a different allocation to a resource on a specific
task for a specific period of time? For example, a developer is going to
spend 2 weeks coding something at 100%, but during day 4,5,6 & 7, I want him
allocated to this task 50% of the time, and another task also at 50%. Then
from day 8 (when the second task is done) till the end, have him back to 100%
allocated. I currently do this by manually adjusting the hours on day
4,5,6,7 in the Resource Usage View, but I am looking for an easier way to set
up the task rather than manually adjusting the work hours. Would some how
using a hammock task work? I also don’t want to create 3 separate task items
either.
task for a specific period of time? For example, a developer is going to
spend 2 weeks coding something at 100%, but during day 4,5,6 & 7, I want him
allocated to this task 50% of the time, and another task also at 50%. Then
from day 8 (when the second task is done) till the end, have him back to 100%
allocated. I currently do this by manually adjusting the hours on day
4,5,6,7 in the Resource Usage View, but I am looking for an easier way to set
up the task rather than manually adjusting the work hours. Would some how
using a hammock task work? I also don’t want to create 3 separate task items
either.