Specifying a task

C

circeo

Is there a an installable macro for MS Project that would allow the user to
specify whether a task is 'capital' or 'expense'

Thanks.
 
R

Rod Gill

Hi,

No, but insert the field Flag1, rename it expense then set it to Yes for
Expensed tasks. Default No is then Capital. You can select Project, Group
and create a group based on the contents of Flag1 field.
 
K

kcirceo

That did the trick, Rod. Thanks.

Rod Gill said:
Hi,

No, but insert the field Flag1, rename it expense then set it to Yes for
Expensed tasks. Default No is then Capital. You can select Project, Group
and create a group based on the contents of Flag1 field.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top