Specifying a work distributed across a number of days

P

Paddy

I need help on how to schedule the following in MS Project 2003, prof
edition. Thanks in advance for your help

I have 3 tasks to schedule.

Task 1 - Total work 2 days - Work will be done 0.5 days each day (AM
sessions) and will end after 4th day by lunch
Task 2 - Total work 1.5 days - Work will be done 0.5 days each day (PM
sessions) and will end after 3rd day by lunch

Task 3 - Total work 1 day - Work will be done 0.5 days each day will start
after task 2 is complete (on the 4th day).
 
D

Dale Howard [MVP]

Paddy --

Task 1 -- Set the Duration to 4 days. Assign the resource to work 50% Units
on the task.

Task 2 -- Set the Duration to 3 days. Assign the resource to work 50% Units
on the task.

Task 3 -- Link this task to Task 2 with a Finish to Start dependency. Set
the Duration to 2 days. Assign the resource to work 50% Units on the task.

Hope this helps.
 