I need help on how to schedule the following in MS Project 2003, prof
edition. Thanks in advance for your help
I have 3 tasks to schedule.
Task 1 - Total work 2 days - Work will be done 0.5 days each day (AM
sessions) and will end after 4th day by lunch
Task 2 - Total work 1.5 days - Work will be done 0.5 days each day (PM
sessions) and will end after 3rd day by lunch
Task 3 - Total work 1 day - Work will be done 0.5 days each day will start
after task 2 is complete (on the 4th day).
edition. Thanks in advance for your help