A
Andrew Lindsay
Hello, I am using Microsoft Project 2007 SP2.
I have a project that is set up to operate 27-7.
I would like to be able to enter start times for my project events down
to the minute, an example of the sort of information is as follows...
Act ID Description B Start B Comp Duration
IN INSTALLATION - AUDACIA 15/01/2009 14:24 16/10/2009 10:45 6572:21
AUI AUDACIA 10/02/2009 0:01 18/09/2009 6:06 5286:05
AUMO Mobilisation Audacia 10/02/2009 0:01 26/02/2009 20:20 404:19
AU110 Project mobilisation activities Audacia (Malaysia) 10/02/2009
0:01 11/02/2009 0:01 24:00
AU100 Mobilise nautical crews AU 10/02/2009 0:01 11/02/2009 0:01 24:00
AU120 Sail to Field 11/02/2009 0:01 23/02/2009 0:01 288:00
1968 Infield mobilisation 23/02/2009 0:01 26/02/2009 8:20 80:19
AU130 DP trials 26/02/2009 8:20 26/02/2009 20:20 12:00
AUAP APS / Sleeper installation 26/02/2009 20:20 2/03/2009 9:43 85:23
AU220 Sleeper installation (10 sleepers) 26/02/2009 20:20 28/02/2009
20:20 48:00
How do I do this in Microsoft Project? I can only seem to enter whole
days for the start date and time.
I have a project that is set up to operate 27-7.
I would like to be able to enter start times for my project events down
to the minute, an example of the sort of information is as follows...
Act ID Description B Start B Comp Duration
IN INSTALLATION - AUDACIA 15/01/2009 14:24 16/10/2009 10:45 6572:21
AUI AUDACIA 10/02/2009 0:01 18/09/2009 6:06 5286:05
AUMO Mobilisation Audacia 10/02/2009 0:01 26/02/2009 20:20 404:19
AU110 Project mobilisation activities Audacia (Malaysia) 10/02/2009
0:01 11/02/2009 0:01 24:00
AU100 Mobilise nautical crews AU 10/02/2009 0:01 11/02/2009 0:01 24:00
AU120 Sail to Field 11/02/2009 0:01 23/02/2009 0:01 288:00
1968 Infield mobilisation 23/02/2009 0:01 26/02/2009 8:20 80:19
AU130 DP trials 26/02/2009 8:20 26/02/2009 20:20 12:00
AUAP APS / Sleeper installation 26/02/2009 20:20 2/03/2009 9:43 85:23
AU220 Sleeper installation (10 sleepers) 26/02/2009 20:20 28/02/2009
20:20 48:00
How do I do this in Microsoft Project? I can only seem to enter whole
days for the start date and time.