Specifying Time of Day Task is due

F

Fo Mo Co

I would like to specify the time of the day the task is due. Weither its in
the morning at 8:00 am or in the evening at 5:00 pm. It would make a
difference of a day in the plan.

Is there a way to specify the time of day that a task is due?

Second. I've created a TEXT Column with "@ 8:00 am". I wanted to at it to
the "start" date on the GANTT format bar. They would be on the same line.
Any way to do that?
 
J

Jan De Messemaeker

Hi,

EVERY time you specify a date in Project you can enter it including time of
day
f.i. 4/7/05 13:33
If you also want these time displayed you have to go to Tools, Options,View
nd choose a Dat format including time of day.
HTH
 
S

Steve House [MVP]

Isn't a task due when it is supposed to finish, not start? I'd suggest
using the Deadline field to specify your due dates. Entering dates into
either the start or finish field always establishes a constraint which is
rarely asppropriate.
 
F

Fo Mo Co

How do deadline and milestones relate? Lets say I have a Material Received
Date milestone of 15 OCT 2004. Would I make the deadline 15 OCT 2004 @ 8:00
am?

If I'm creating a template for future project, would moving the milestone in
the planning stage also move the deadline? Or would I have to manually move
the deadline with it?
 
F

Fo Mo Co

Acutally, I'm letting the milestone slide relative to another milestone. So
I'm not setting the date. But, the task must be delivered at 8:00 am the
morning of the Milestone. If its later, then we have to wait an additional
day.

I could put in a task: "Wait 24 hrs before ....." and assign 24 hrs duration?
 
S

Steve House [MVP]

There is sometimes confusion about what milestones are. They are NOT dates
themselves but they do occur on at some specific date and time. The
milestone itself is the event that takes place - a contract has been signed,
a final report has been completed, a critical part has been delivered, a
project phase has been completed, etc - that has some special signifigance
in the project. It occurs whenever it occurs and even though there may be a
target or desired date, just like any other event the milestone event itself
might take place early, on-time, or late. In other words, you have TWO
dates associated with your milestone event - the date when it WILL occur and
the date by which it SHOULD occur. (I should point out that milestones
don't necessarily have a due date - remember the milestone is an event and
even though it's important to monitor for project tracking purposes we might
not actually care when it happens.) In engineering you could say that the
milestone marks a state change - in erecting a building before the milestone
"foundation ready" the construction of the foundation is in process. The
milestone marks the point where the foundation is complete and we can move
on to the next phase. The change of state is "foundation incomplete" ->
"foundation ready."

In your example the milestone is the receipt of the material. You need it
by Oct 15th so that is its deadline. But the delivery might come in a week
before, on the 15th, or there might be a trucker's strike and your material
might not get there until November. The date shown in the Gantt chart is
the estimated date based on links leading to it, including lag times, until
it has occured and then the actual date on which it did occur. By entering
a deadline on the Task Information sheet, Advanced tab, for the milestone
you can put a green arrowhead marker on the Gantt chart to indicate what the
"drop dead" date of the milestone is and to see whther you're making the
required schedule or not.

Moving the milestone will not move the deadline nor should it. If we had to
have parts received by 15th October last year does that mean in a similar
project next year we'll need the same delivery date? Not very likely.


--
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top