P
Peter S.
I am using Microsoft Project Server, but I cannot get SPI for any of my tasks
to be >1 --- even if the task is baselined as a two week duration task
baselined to finish 1 week from today, it is 100% complete, and it was
finished today! This works on the standalone version, but in the server
version
to be >1 --- even if the task is baselined as a two week duration task
baselined to finish 1 week from today, it is 100% complete, and it was
finished today! This works on the standalone version, but in the server
version