P
Procekt
Hi:
I am stuck in 2 issues. Any kind of help is greatly appreciated.
1. I am trying to calculate CPI and SPI through creating a new column and
then creating the formula manually. (I don't have version 2003). No problem
until here.
However, after calculating the values for each task, MS Project displays an
integer value which is either 1 or 0. Does anybody know how to display these
value up to 2 decimals, somehting lik 1.00 or 0.94 or 1.03 etc.
2. As a resource I am using a group of people instead of a single person.
(Since their payment is made accordingly). This group of people are assigned
multiple tasks in any given duration. They have the capacity to perform
multiple tasks in any specific day. By default, MS Project thinks that if you
assign doble task to this group they overallocated. ( by %200, %400 or %800).
Thus, Their total cost overall sums up to $80000 instead of $40000. I tried
to manipulate this manually by changing the max unit levels to higher values
or assigning a %50 workload if they have two different tasks in a single they
but could not overcome the problem.
I hope I was clear enough.
Thanks
I am stuck in 2 issues. Any kind of help is greatly appreciated.
1. I am trying to calculate CPI and SPI through creating a new column and
then creating the formula manually. (I don't have version 2003). No problem
until here.
However, after calculating the values for each task, MS Project displays an
integer value which is either 1 or 0. Does anybody know how to display these
value up to 2 decimals, somehting lik 1.00 or 0.94 or 1.03 etc.
2. As a resource I am using a group of people instead of a single person.
(Since their payment is made accordingly). This group of people are assigned
multiple tasks in any given duration. They have the capacity to perform
multiple tasks in any specific day. By default, MS Project thinks that if you
assign doble task to this group they overallocated. ( by %200, %400 or %800).
Thus, Their total cost overall sums up to $80000 instead of $40000. I tried
to manipulate this manually by changing the max unit levels to higher values
or assigning a %50 workload if they have two different tasks in a single they
but could not overcome the problem.
I hope I was clear enough.
Thanks