I
invincible
I am trying to calculate the SPI for all possible cases using
Microsoft Project 2007.
The SPI calculation is working fine for the cases in which BCWP < BCWS
i.e. when SPI
is less than one..But for the cases in which BCWP > BCWS it is giving
the SPI as 1 and not greater than one..On close inspection i found
that in the resource usage table , watever extra work has been done on
a day is shifted to the next day..Thus if im setting my status date to
the current date , it is giving SPI equal to one..I hope u get my
problem!!
Is this a bug in MS Project?? If not what is the way out of it??
Thanking you in advance.
Cheers,
Shishir.
Microsoft Project 2007.
The SPI calculation is working fine for the cases in which BCWP < BCWS
i.e. when SPI
is less than one..But for the cases in which BCWP > BCWS it is giving
the SPI as 1 and not greater than one..On close inspection i found
that in the resource usage table , watever extra work has been done on
a day is shifted to the next day..Thus if im setting my status date to
the current date , it is giving SPI equal to one..I hope u get my
problem!!
Is this a bug in MS Project?? If not what is the way out of it??
Thanking you in advance.
Cheers,
Shishir.