B
Brian Lukanic
I have a Baselined Project.
In doing some "what-if" scenarios for tasks that are scheduled to occur well
into the future, I assign 100% complete to a task that is 3 months out. The
resulting SPI value for it and its summary task shoots up well beyond a value
of 1; I'm talking goofy numbers like 13, 27.xx, etc.
My feeling with SPI is that a get-ahead task should still result only in a
value of 1 - that's the ceiling no matter how early something gets done. Is
this a fair expectation to have? Does Project behave differently? If so, is
there any way to configure Project so that anything above 1 gets "rounded
down" to 1?
In doing some "what-if" scenarios for tasks that are scheduled to occur well
into the future, I assign 100% complete to a task that is 3 months out. The
resulting SPI value for it and its summary task shoots up well beyond a value
of 1; I'm talking goofy numbers like 13, 27.xx, etc.
My feeling with SPI is that a get-ahead task should still result only in a
value of 1 - that's the ceiling no matter how early something gets done. Is
this a fair expectation to have? Does Project behave differently? If so, is
there any way to configure Project so that anything above 1 gets "rounded
down" to 1?