G
Gary Zag
Is there a way for the person assigned a task to show a delay in finishing a
task once it was started from PWA? In PWA 2003 you could enter 0 hours for
days up to when you thought you would get back to working on the task. When
accepted into the schedule it would show it as a split task. Is there a way
to do this in PWA 2007?
Gary
task once it was started from PWA? In PWA 2003 you could enter 0 hours for
days up to when you thought you would get back to working on the task. When
accepted into the schedule it would show it as a split task. Is there a way
to do this in PWA 2007?
Gary