ProjectRita
hi,
I was already seeing some of the answers on this subject, but I am not
convinced. It happens that in my project I have 2 types of calendars, one
(CALENDAR1) the weekend is considered as non-working days (this include
almost every activitie), and in the other saturday is a working day
to(CALENDAR2). I can see that is possible to hide the bar tasks on weekends,
selecting the non-working time to be in front of tasks bars, but i have tried
to change the option for the activities that have the second calendar, but
the calendar returns to the base format. Is it possible to do 2 format types,
for different calendars? If the answer ir no, is there a way that i can make
a collum with the split days for each activities? I ask this, because this
will be something that i will have to do every week, but the project that i
have to deliver only have 3 weeks, so there only be 3 weekends, and for that
the split days will be the same for all activities in calendar 1. I`m
allready thinking in another option, if i don`t have a positive return on
this questions...maybe the only way, is to do a box, in the weekend bars that
only hide the task bars on weekends that belong to calendar1.
Thanks for the attention...
Regards
I was already seeing some of the answers on this subject, but I am not
convinced. It happens that in my project I have 2 types of calendars, one
(CALENDAR1) the weekend is considered as non-working days (this include
almost every activitie), and in the other saturday is a working day
to(CALENDAR2). I can see that is possible to hide the bar tasks on weekends,
selecting the non-working time to be in front of tasks bars, but i have tried
to change the option for the activities that have the second calendar, but
the calendar returns to the base format. Is it possible to do 2 format types,
for different calendars? If the answer ir no, is there a way that i can make
a collum with the split days for each activities? I ask this, because this
will be something that i will have to do every week, but the project that i
have to deliver only have 3 weeks, so there only be 3 weekends, and for that
the split days will be the same for all activities in calendar 1. I`m
allready thinking in another option, if i don`t have a positive return on
this questions...maybe the only way, is to do a box, in the weekend bars that
only hide the task bars on weekends that belong to calendar1.
Thanks for the attention...
Regards