D
DaveNmo
I have over 2300 projects in PS2003 and PWA is taking too long to refresh.
Over half of the projects are completed, so I plan to migrate them to a new
instance of Project Server (using the Site Editor tool).
I have the following questions:
1. Will I select "Single Database Configuration" since there is only one SQL
Server and one instance of the Project Server database?
2. Will I gain performance if choosing "Standard 2-way Deployment"? I
believe the goal is to create a separate instance of Project Server, a
separate PWA site with only active projects (and an archive PWA site for
closed projects), and a separate OLAP cube for each (unless one OLAP cube is
possible for both).
3. How do I migrate "completed" projects to the new database?
4. Will I need to manually re-create the enterprise resource pool in the
"archive" project server?
5. Are there any books or other reference materials on this topic? The
Thanks in advance for your reply.
David Nash
Over half of the projects are completed, so I plan to migrate them to a new
instance of Project Server (using the Site Editor tool).
I have the following questions:
1. Will I select "Single Database Configuration" since there is only one SQL
Server and one instance of the Project Server database?
2. Will I gain performance if choosing "Standard 2-way Deployment"? I
believe the goal is to create a separate instance of Project Server, a
separate PWA site with only active projects (and an archive PWA site for
closed projects), and a separate OLAP cube for each (unless one OLAP cube is
possible for both).
3. How do I migrate "completed" projects to the new database?
4. Will I need to manually re-create the enterprise resource pool in the
"archive" project server?
5. Are there any books or other reference materials on this topic? The
Thanks in advance for your reply.
David Nash