Split of tasks

K

Kay

Dear all,
I use MS Project 2003 SP 2 Standard.
I try to do the most simple planning.
One resource, who does some tasks, one after another.
So I entered it.
30% admin work over the entire time
70% work for the tasks.
So I entered admin time and assigned the resource for 30%.
Then I entered the tasks, all fixed work, and entered
the tasks, entered the resource and the work effort.
So 7 days for one task one mean a 10 day duration.
So far so good. But suddenly MSP splits up tasks,
which I haven't seen before.
What do I do wrong? Why is MSP doing it?
And how can I avoid it?

Regards

Kay
 
D

Dave

Do you have levelling set to automatic (Tools/Level Resources)?

Turn this off.

You may also have your levelling set to too fine a granularity. Set the
levelling to level only on a week-by-week or month-by-month basis.

To get it back, clear the levelling (Tools/Level Resources).

Dave
 
K

Kay

Do you have levelling set to automatic (Tools/Level Resources)?
Turn this off.

Damn
yes it is.
The first time it was this way installed. Before my company always
installed it with this set to off
You may also have your levelling set to too fine a granularity.  Set the
levelling to level only on a week-by-week or month-by-month basis.
good point
To get it back, clear the levelling (Tools/Level Resources).

I will
Thanks
Kay
 