J
John M
I want to split a Gantt chart bar into 3 segments & decide when each segment
begins & ends. For example, segment one should begin 06/01/07 and end
06/08/07; segment two should begin 08/16/07 and end 08/23/07, and segment
three should begin 05/01/08 and end 06/20/08. (I don't want to define these
as different tasks requiring additional rows on the Gantt chart.)
Thanks to any Project genius who can help.
begins & ends. For example, segment one should begin 06/01/07 and end
06/08/07; segment two should begin 08/16/07 and end 08/23/07, and segment
three should begin 05/01/08 and end 06/20/08. (I don't want to define these
as different tasks requiring additional rows on the Gantt chart.)
Thanks to any Project genius who can help.