D
davegb
I have split tasks in my projects where the split was lengthened, then
later shortened. While the normal blue bar ends at the correct,
earlier date, there is a trail of dots following the to the right of
the end of the blue bar, and the tasks finish date is the date where
the trail of dots ends, not where the blue bar ends. I want the finish
date to be the end of the blue bar, and to remove the trail of dots to
the right of it. Has anyone seen this before? Anyone know a fix for
this?
Dave Bellamy
Bellamy Consulting
later shortened. While the normal blue bar ends at the correct,
earlier date, there is a trail of dots following the to the right of
the end of the blue bar, and the tasks finish date is the date where
the trail of dots ends, not where the blue bar ends. I want the finish
date to be the end of the blue bar, and to remove the trail of dots to
the right of it. Has anyone seen this before? Anyone know a fix for
this?
Dave Bellamy
Bellamy Consulting