M
Markemark
Hi
I have a Project which contains a task which is 20 days long. 10 days into
the 1st task, it is stopped while another task takes place for 5 days. After
which, the original task continues.
How should this be done in Project? Should the first task be a split task?
If so, how do I link the 2nd task to the 1st, mid-way though the 1st task?
Or should I split the first task into two seperate tasks with second task
placed between them, using Finish to Start relationship?
Thanks
I have a Project which contains a task which is 20 days long. 10 days into
the 1st task, it is stopped while another task takes place for 5 days. After
which, the original task continues.
How should this be done in Project? Should the first task be a split task?
If so, how do I link the 2nd task to the 1st, mid-way though the 1st task?
Or should I split the first task into two seperate tasks with second task
placed between them, using Finish to Start relationship?
Thanks