T
Trevor Rabey
I hate split Tasks and avoid modeling with them.
...but
If you split Tasks, even multiple times, the duration stays the same, say 5
Days...
So one 5 day Task split into bits with 4 spaces, ie:
1 day of Task, 1 day of Space,1 day of Task, 1 day of Space,1 day of Task, 1
day of Space, 1 day of Task, 1 day of Space, 1 day of Task.
still has a duration of 5 days, even though it is "spread" over 9 days. OK,
Duration measures Working Days (according to the calendar for the Task).
....Unless the Task Type is Fixed Duration, and this happens even if there
are no Resources or Work.
Why the difference due to Type and what purpose does it serve?
...but
If you split Tasks, even multiple times, the duration stays the same, say 5
Days...
So one 5 day Task split into bits with 4 spaces, ie:
1 day of Task, 1 day of Space,1 day of Task, 1 day of Space,1 day of Task, 1
day of Space, 1 day of Task, 1 day of Space, 1 day of Task.
still has a duration of 5 days, even though it is "spread" over 9 days. OK,
Duration measures Working Days (according to the calendar for the Task).
....Unless the Task Type is Fixed Duration, and this happens even if there
are no Resources or Work.
Why the difference due to Type and what purpose does it serve?