I have a plan with no completed tasks and with all tasks assigned to a
single resource. Each resource is assigned at 66%. Even when I clear
levelling, and have "Levelling can create splits in remaining work", I
find that tasks are split seemingly at random - you can see what I mean
on this screencap:
http://i9.tinypic.com/2yycj0p.gif
Does anyone know how I prevent tasks splitting at all?
I'm using Project Standard 2003 SP2, incidentally.
Thanks,
P.