D
Dave
I would like to pull out IS resource costs from the overall costs. IS
versus Non-IS employees are identified in the OBS. So, for example, I
have a project with 3 tasks as follows (and all resources have a rate
of $50/hr.):
Task 1/Bill (IS )/8 hrs /$400 cost
Task 2/Fred (Non-IS)/8 hrs /$400 cost
Task 3/Bill & Fred /8 hrs each/$800 cost
In that scenario, the total cost is $1600. The IS Cost is $800. Any
suggestions on how I can calculate the IS Cost automatically?
Thanks.
versus Non-IS employees are identified in the OBS. So, for example, I
have a project with 3 tasks as follows (and all resources have a rate
of $50/hr.):
Task 1/Bill (IS )/8 hrs /$400 cost
Task 2/Fred (Non-IS)/8 hrs /$400 cost
Task 3/Bill & Fred /8 hrs each/$800 cost
In that scenario, the total cost is $1600. The IS Cost is $800. Any
suggestions on how I can calculate the IS Cost automatically?
Thanks.