Nuala
Any advice please
We have installed service pack one on the project server 2003 and have
rolled out the project pro service pack to some users. We are using
timesheeting to report actual work
Subsequent to the installation of the service pack all project
managers have had a spooler error on updating of actuals and saving
the plan the error is preventing us from republishing the plan and
therefore is not coming through to the OLAP for portfolio analyser.
The error message is
Message Type Error
Publish New and changed assignements 0x800A0CC1
The other information just refers to the plan date and project
manager.
We have recieved this message on all project plans, so it is not user
specific.
TIA
Nuala
We have installed service pack one on the project server 2003 and have
rolled out the project pro service pack to some users. We are using
timesheeting to report actual work
Subsequent to the installation of the service pack all project
managers have had a spooler error on updating of actuals and saving
the plan the error is preventing us from republishing the plan and
therefore is not coming through to the OLAP for portfolio analyser.
The error message is
Message Type Error
Publish New and changed assignements 0x800A0CC1
The other information just refers to the plan date and project
manager.
We have recieved this message on all project plans, so it is not user
specific.
TIA
Nuala